Booster Collimator System
Basic Idea…
• Unshielded copper secondary collimators were installed in summer 2002,
with a plan to shield them later.
• Due the the unexpected extent of the shielding and the difficulty of working
in the area, the design was ultimately abandoned as unacceptable.
• Collimators were removed during the January shutdown.
• A new collimator system is being designed with steel secondary jaws fixed
within a movable shielding body.
• Hope to have then ready before summer shutdown.