Booster Operation in Support of the Collider Program
Eric Prebys Accelerator Technology Seminar, March 18, 2003 |
Booster Extraction (Long 3 and Long 13)
Every long and short section (2x24=48) has | |||
A horizontal and vertical BPM | |||
Can read out turn by turn for two or 50 time points for all 96 | |||
A beam loss monitor | |||
Can snapshot all 96 for each cycle | |||
Horizontal and vertical trims | |||
Originally DC. Working on active control for the 24 high-b ones in each plane. | |||
Quads and Skew Quads | |||
Each has an individual DC setting plus common ramp. | |||
Chromaticity sextupoles controlled by ramps | |||
Some individual loss monitors at key locations. | |||
Horizontal pinger for tune measurement | |||
Couples to V plane | |||
Doesn’t work at the moment (had to steal kicker) |
8 GeV Proton Run II Goals and Performance
Beam Loss Intensity Sensitivity
The proton source is very close the the specifications in the Run II Handbook. | |
Although it’s the highest priority, support of collider operations is a relatively minor facet of life in the proton source. | |
Proton source activities are dominated by the current and projected needs of the neutrino program (MiniBooNE+NuMI+??) | |
Whatever a WBS chart may say, there’s not a separate proton source for RunII, MiniBooNE, NuMI, etc. |
Limitations to Total Booster Flux
Total protons per batch: 4E12 with decent beam loss, 5E12 max. | |||
Average rep rate of the machine: | |||
Injection bump magnets (7.5Hz) | |||
RF cavities (7.5Hz, maybe 15 w/cooling) | |||
Kickers (15 Hz) | |||
Extraction septa (was 2.5Hz, now 15Hz) | |||
Beam loss | |||
Above ground: | |||
Shielding | |||
Occupancy class of Booster towers | |||
Tunnel losses | |||
Component damage | |||
Activiation of high maintenance items (particularly RF cavities) |
Everything measured in 15 Hz “clicks” | |||
Minimum Main Injector Ramp = 22 clicks = 1.4 s | |||
MiniBoone batches “sneak in” while the MI is ramping. | |||
Cycle times of interest | |||
Min. Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s | |||
Min. NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s | |||
Full “Slipstack” cycle (total 11 batches): | |||
6 inject + 2 capture (6 -> 3) + 2 inject + 2 capture (2 -> 1) + 2 inject + 2 capture (2 -> 1) + 1 inject + 22 M.I. Ramp ---------------------- 39 clicks = 2.6 s |
The Time Line Generator (TLG) sequences all accelerator operations. | ||
Traditionally, each sequence (“module”) is independent, including any necessary Booster prepulses. | ||
This wasn’t really compatible with the goal of getting the maximum possible beam out of the Booster. | ||
In the new scheme: | ||
Standalone sequences are placed in the time line, with necessary prepulses | ||
MiniBooNE pulses are “trailer-hitched” to the end of these to achieve a specified average repetition rate, subject to an overall total rate. | ||
If there aren’t enough modules to trailer-hitch to, new modules will be built (still working the bugs out of this one). |
Booster Losses (Normalized to Trip Point)
Booster Tunnel Radiation Levels
Some Cold Hard Facts about the Future
Running as we are now, the Booster can deliver a little over 1E20 protons per year – this is about a factor of six over typical stacking operations, and gives MiniBooNE about 20% of their baseline. | |
NuMI will come on line in 2005, initially wanting about half of MiniBooNE’s rate, but hoping to increase their capacity – through Main Injector Improvements – until it is equal to MiniBooNE. | |
Whatever the lab’s official policy, there will be great pressure (and good physics arguments) for running MiniBooNE and NuMI at the same time. | |
-> By 2006 or so, the Proton Source
might be called upon to deliver 10 times what it is delivering now. |
|
At the moment, there is no plan for assuring this, short of a complete replacement! | |
So what are we going to try?… |
Some Things Which Have Been Done
Shielding and new radiation assessment | |
Vastly improved loss monitoring. | |
New (MP02) extraction septum and power supply (enable high rep. rate running) | |
New tuning strategies. |
Unshielded copper secondary collimators were installed in summer 2002, with a plan to shield them later. | |
Due the the unexpected extent of the shielding and the difficulty of working in the area, the design was ultimately abandoned as unacceptable. | |
Collimators were removed during the January shutdown. | |
A new collimator system is being designed with steel secondary jaws fixed within a movable shielding body. | |
Hope to have then ready before summer shutdown. |
The existing RF cavities form the primary aperture restriction (2 ¼” vs. 3 ¼”). | |
They are high maintenance, so their activation is a worry. |
There is a plan for a new RF system with 5” cavities: | ||
Powered prototype built | ||
Building two vacuum prototypes for the summer shutdown with substantial machining done at universities. | ||
Evaluate these and procede (hopefully?) with full system. | ||
Total cost: $5.5M cavities + $5.5M power supplies (power supplies would pay for themselves in a few years) | ||
Is it worth it? On of the questions for the study group is how much improvement we might expect. |
The current injection bump dogleg (ORBUMP) magnets can ramp at 7.5 Hz, with a substantial temperature rise. | ||
Need to go to 10 to support MiniBooNE and NuMI. | ||
2 spares for the 4 (identical) magnets. Most likely failure mode probably repairable. | ||
Considering new design which will stretch existing magnets further apart, which will lower their current, but will require a pulsed injection septum between the first two. | ||
Can new design incorporate injection improvements?? | ||
Some power supply issues as well: | ||
One full set of replacement SCR’s for the switch network. | ||
New switchbox being designed, but needs attention (or order more spare SCR’s). | ||
No spare for charge recovery choke. |
In order to Reduce radiation, a “notch” is made in the beam early in the booster cycle. | |
Currently, the extraction time is based on the counted number of revolutions (RF buckets) of the Booster. This ensures that the notch is in the right place. | |
The actual time can vary by > 5 usec! | |
This is not a problem if booster sets the timing, but it’s incompatible with multi-batch running (e.g. Slipstacking or NuMI) | |
We must be able to fix this total time so we can synchronize to the M.I. orbit. | |
This is called “beam cogging”. |
Detect slippage of notch relative to nominal and adjust radius of beam to compensate. |
Historically, the booster has lacked a fundamental understanding of beam loss mechanisms. | ||
If (!!!) it is possible at all to go the the required beam flux, it will require some mitigation of beam loss. | ||
Recently, there has been an great increase in the involvement of the Beam Physics department in the Booster: | ||
Space charge group (W. Chou, et al) has begun to focus on the Booster again. | ||
Chuck Ankenbrandt has moved into Booster group as “Beam Physics Liaison” to help coordinate studies. | ||
Starting to make quantitative comparisons between predictions and measurement. | ||
An almost immediate result of this increased effort was the discovery of the “dogleg problem”…. |
Took advantage of recent TeV Magnet failure to raise the Long 13 (dump) septum and turn off the associated dogleg. | |
Doglegs almost exactly add, so this should reduce the effect by almost half. | |
The mode of operation prevents short batching, booster study cycles and RDF operation. | |
Had about 36 hours of study in this mode. | |
Bottom Line: major improvement. |
Tune to minimize current? | ||
helped so far, but near limit. | ||
Maybe raise L13 septum a bit? | ||
Motorize L13 septum to switch modes quickly? | ||
Operational nightmare | ||
Eliminate L13? | ||
Find another way to short-batch | ||
Make a dump in MI-8 for Booster study cycles? | ||
Correctors?: | ||
These don’t look like quads, so can’t find a fix – yet. | ||
Spread out doglegs (effect goes down with square of separation): | ||
Not a lot of room. Maybe separate downstream magnets? | ||
Three-legged dog? | ||
Turn of the third of the four magnets. | ||
Need to increase first two reduces net improvement. |
Large Aperture Lattice Magnets? | ||
Obviously the “right” idea. | ||
Must match lattice AND (preferrably work with existing resonant circuit). | ||
Potential for big screw-up. | ||
Pulsed extraction bump? | ||
Straightforward magnet design. | ||
Only part of the lattice for a short period at the end of the cycle. | ||
New ideas welcome. |
Longevity Issues (non-radiation)
GMPS (upgraded, OK) | ||
Transformers (serviced, OK) | ||
Vacuum system (being updated, finished 2003) | ||
Kicker PS charging cables | ||
Run three times over spec | ||
Evaluating improved design (better cable, LCW-filled heliac, etc) | ||
Low voltage power supplies, in particular Power 10 Series: | ||
Unreliable, some no longer serviced. | ||
Starting search for new supplier and evaluate system to minimize number of different types. | ||
Probably a few $100K to upgrade system. |
Longevity Issues (non-radiation, cont’d)
RF Hardware | ||
(original) Copper tuner cooling lines are beginning to spring leaks. Difficult to repair because they’re hot. | ||
High Level RF | ||
More or less original. | ||
Our highest maintenance item. | ||
Will probably last, BUT expensive to maintain. | ||
John Reid and Ralph Pasquinelli feel a new solid state system would pay for itself ($5.5M) in about four years. | ||
Low Level RF | ||
Many old modules, some without spares, some without drawings. | ||
An upgrade plan in place. | ||
Not expensive, but NEED people. | ||
Personnel!!!! |
Cables: frequent replacement of HV cables and connectors for ion pumps. | |
Hoses: valve actuator hoses have failed and are now being replaced with stainless steel. | |
Kicker magnets: A kicker which recently failed showed signs of radiation damage to the potting rubber. | |
Main magnet insulation: No main magnets have failed in 30 years, but… | |
Installed radiation “dose tabs” around the ring in January shutdown to get a real estimate of dosage. |
The Fermilab Booster has maintained a remarkable level of reliability over the last 30 years. | |
It has now reached unprecedented performance levels while maintaining reasonably strict beam loss standards. | |
We still have a lot to do to meet the demands of the future. |