Booster Studies Schedule
-
Monday, 1/27
-
day: Establish beam in Booster. Do MP02 aperture scan. Return
beam to pre-shutdown quality. Pulse MP02 power supply. (Tomlin, Lackey)
Fire up gamma-t in parallel (Pellico)
-
20-24: Aperture scans (Coney, Prebys)
-
Tuesday, 1/28
-
0-8: Aperture scans continue (Coney, Prebys)
-
day: continue MP02 pulsing, beam optimization, and parasitic gamma-t work.
-
18-??: Secure M.I. and extract beam (Lackey).
-
Wednesday, 1/29
-
8-4: Fire up Gamma-t. system. Look at beam steering and attempt
to center beam in quads. Look at stability of beam for high intensity
with the long. damping system. Perhaps try to spoil the beam with
the "fuzzer" (Tomlin, Lackey, Prebys, Pellico).
-
16-24: Lattice measurement (Coney, Prebys) [unless we have
to take another stab at extracting beam].
-
Thursday, 1/30
-
0-12: Go to DC. Shake down McGinnis' program and do resonance scans
(Spentz, Pellico, McGinnis, Sullivan).
-
12-16: DC Acceptance measurement (Ankenbrandt, Chou, Tomlin)
-
16-20: Emmittance Measurement + ORBUMP painting (Tomlin, Chou)
-
20-24: Beam extinction studies (Prebys)
-
Friday, 1/31
-
0-4: Longitundal filling studies (Prebys+??)
-
4-8: DC chromaticity measurement (Tomlin)
-
8-12: RF Sweep studies + dogleg dispersion measurements (numerous)
-
12-16: IPM aborted beam studies, DC short batch studies (Pellico+??).
-
Saturday, 2/1: more DC dogleg studies.
-
Sunday: return to AC operation.