Kyle Hesse (Thomas Jefferson National Accelerator Facility)
WEP056
LLRF commissioning of the CEBAF C75 upgrades SAM 2024/25
789
An often-overlooked aspect of Low Level Radio Frequency (LLRF) design is commissioning of a new system. During Jlab’s Scheduled Accelerator Maintenance (SAM) in 2024, two C75 Cryomodule were installed in CEBAF with Jlab’s LLRF 3.0 system. Jlab’s team has invested effort in automating and standardizing their commissioning process. Several key components are klystron characterization, cavity characterization, and interlock verification. This poster will present the summary of LLRF preparation and commissioning efforts at Jlab.
Paper: WEP056
DOI: reference for this paper: 10.18429/JACoW-NAPAC2025-WEP056
About: Received: 07 Aug 2025 — Revised: 13 Aug 2025 — Accepted: 14 Aug 2025 — Issue date: 28 Aug 2025